Project Description:
Engineering consultancy works on the implementation and management of the project of constructing 10 ground tanks, (10) + (2) ground tanks in Wadi Al-Jarafi Nakhl Center Approximate storage capacity = 4500 cubic meters
Construction of Wadi um al-Bared Dam / Establishment of an artificial lake / Strengthening and rehabilitation of existing dams in Wadi Al-Jarafi
1- Rehabilitation and consolidation of 4 dams in Wadi Al-Jarafi Total storage capacity 1.2 M3
2-Implementation of a lake and 5 calming basins in the Awlad Ali area in North Sinai Governorate
The storage capacity of the lake and basins is 1.5 million cubic meters.
3-Implementation of um Al-Bared Dam Length 255 meters and a height of 10 meters And the width from the bottom is 64 meters and from the top 8 meters Earthen barrier with a length of 700 m and a height of 4 m
Client : National General Contracting & Supplies Co.
Project Status: Completed